Ford Otosan Gölcük Press Building

Ground Improvement Details:Jet Grouting: A total of 46,650 linear meters of jet grouting was executed to improve soil conditions. This technique involves injecting a cementitious grout at high pressure to enhance the soil's bearing capacity and reduce the risk of liquefaction and settlement. Bored Pile System: A deep foundation solution was implemented with 8,260 linear meters of bored piles to bypass weak soil layers and provide high load-bearing capacity. Diaphragm Wall: A 4,900 m² diaphragm wall system was constructed for excavation support, slope stabilization, and groundwater control.

Structural Systems: Steel Structure: The main structural system is a steel frame, totaling 3,200 tons. This includes steel columns and a roof structure designed for large clear spans and high loads. Underground Infrastructure: This includes specialized underground systems for press lines, conveyor systems, and machine foundations. Reinforced Concrete Foundations: The facility is founded on reinforced concrete foundations, designed to distribute industrial loads evenly.

Mechanical, Electrical, and Automation Systems: Crane Systems: The facility is equipped with two overhead traveling crane systems: one with a capacity of 60 tons and another with a capacity of 30 tons. Electrical Infrastructure: The power supply is managed by a 2500 kVA transformer, supported by a robust electrical infrastructure including MV/LV switchgear and distribution panels. Automation: A comprehensive automation system was installed, including SCADA and PLC controls, with full integration into the existing factory's systems.

MEP Systems: The project includes complete fire suppression, HVAC (Heating, Ventilation, and Air Conditioning), and fire detection systems. Specialized Areas: Test Rooms: Dedicated areas were constructed for specialized operations, including a teardown and disassembly test room and a tensile test laboratory. These rooms feature reinforced floors, sound insulation, and specialized ventilation. Utility Systems: A 750 m³ underground greywater tank was built for water management. The facility also features well-equipped WC blocks and locker rooms.

Industrial Doors: The building is fitted with a variety of industrial doors, including logistics doors for loading and unloading, and fire-rated emergency exit doors with panic bar systems. Finishing and Site Infrastructure: Cladding: The roof is covered with a composite panel cladding system for thermal insulation and weather protection, while the facade features a cassette panel cladding system for a modern aesthetic and energy efficiency.

Site Development: The surrounding area includes extensive landscaping, paved roads, and logistics infrastructure to support efficient operations.

Total Construction Area: 16,800 m².

Gölcük, Turkey
Completed 2023

Project General Features

This large-scale industrial facility project is a modern production complex with a total construction area of 16,800 m². The project is designed with advanced technological infrastructure, a steel structural system, and integrated automation solutions, ensuring full compliance with industrial production standards.

Ground Improvement Works

Jet Grouting Application

Application Quantity: 46,650 meters

Jet grouting was performed to improve weak soil layers and increase their bearing capacity. This method involves:

In-situ soil improvement with a high-pressure jet system.

Increasing soil stability by injecting a cement mixture.

Achieving uniform bearing capacity.

Preventing settlement issues.

Eliminating the risk of liquefaction.

Bored Pile System

Application Quantity: 8,260 meters

The bored pile application was implemented as part of the deep foundation system:

A high-bearing capacity deep foundation solution.

Secure foundation with a steel pipe pile system.

Bypassing compressible soil layers.

Providing lateral load resistance.

Ensuring long-term stability.

Diaphragm Wall System

Application Area: 4,900 m²

The diaphragm wall application is critical for excavation safety and water control:

Construction of a reinforced concrete diaphragm wall.

Controlling and preventing water seepage.

Resistance against lateral earth pressure.

Ensuring excavation safety.

Serving as a permanent structural element.

Excavation and Filling Works

Earthworks

Comprehensive excavation and filling works include:

Precision excavation works down to foundation levels.

Controlled backfilling with compaction tests.

Drainage systems for water management.

Slope stability for safe working conditions.

Excavation management in compliance with environmental standards.

Ground Preparation

Ground improvement in accordance with geotechnical recommendations.

Compaction tests and quality control.

Spreading and compaction of sub-base material.

Drainage and waterproofing systems.

Reinforced Concrete Foundation Systems

Foundation Design

A reinforced concrete foundation system resistant to industrial loads:

Raft foundation for uniform load distribution.

Isolated footings at column points.

Tie beams for horizontal stability.

Waterproofing for groundwater protection.

Expansion joints for thermal movements.

Concrete Quality

Minimum concrete class of C30/37.

Controlled water-to-cement ratio.

Tested aggregate quality.

Admixtures for durability.

Curing process in compliance with standards.

Underground Infrastructure Systems

Press Line Construction

Underground press lines are critical infrastructure for operational continuity:

Compressed air lines for production machinery.

Hydraulic lines for power transmission.

Vacuum systems for special applications.

Protective conduits against mechanical damage.

Maintenance access with service hatches.

Conveyor Line Construction

Underground infrastructure for material handling systems:

Conveyor trenches with reinforced concrete construction.

Electrical infrastructure for motor power supply.

Control cables for the automation system.

Drainage systems for moisture control.

Access points for maintenance and repair.

Machine Foundations

Special foundations for heavy industrial machinery:

Vibration isolation for vibration damping.

High bearing capacity for heavy loads.

Precision positioning for machine alignment.

Anchorage systems for machine fastening.

Cable channels for electrical connections.

Steel Structural System

Steel Construction Details

Total Steel Quantity: 3,200 tons

Steel Columns

IPE/HEB etc. profiles based on load-bearing capacity.

Corrosion protection.

Fire resistance with a painting system.

Connection details with welding and bolted connections.

Foundation anchors for a secure connection.

Steel Roof System

Steel truss girders for wide spans.

Purlin systems for roof slope.

Wind bracing for lateral stability.

Connection elements for structural integrity.

Expansion joints for thermal movements.

Assembly Process

Fabrication in a workshop environment.

Quality control with NDT tests.

Logistics planning for dimensional optimization.

On-site erection with cranes.

Welding works by certified welders.

Utilities Galleries

Rooftop Utilities Galleries

Special gallery system for mechanical and electrical utilities:

Steel construction for durability.

Weather resistance for outdoor use.

Maintenance access for safe work.

Cable tray systems for electrical lines.

Pipe supports for mechanical lines.

Indoor Utilities Routes

Suspended ceiling for ceiling-level passages.

In-wall conduits for concealed utilities.

Floor trenches for heavy lines.

Vertical shafts for inter-floor connections.

Service rooms for equipment placement.

Crane Systems

60-Ton Overhead Traveling Crane System

For heavy lifting operations:

Double-girder design for high capacity.

Variable frequency drive for precise control.

Anti-sway system for load stabilization.

Wireless remote control for operator safety.

Maintenance platforms for service access.

30-Ton Overhead Traveling Crane System

For medium-capacity lifting:

Single-girder economical design.

Hoist system for electric lifting.

Travel system for movement on rails.

Safety systems for overload protection.

Positioning for precise placement.

Crane Rails and Supports

Crane rails made of high-quality steel.

Rail connections with welding and bolts.

Buffer systems for impact absorption.

Electrical lines for power supply.

Maintenance walkways for safe access.

Roof and Facade Claddings

Composite Panel Roof Cladding

High-performance roof cladding system:

Sandwich panel structure with thermal insulation.

Waterproofing with a membrane system.

Vapor barrier for moisture control.

Wind resistance with mechanical fastenings.

Thermal break for energy efficiency.

Cassette System Facade Cladding

A modern and functional facade solution:

Shaped and painted sheet metal cassette panels for a lightweight and durable finish.

Thermal break for thermal insulation.

Air tightness for energy saving.

Aesthetic appearance with a modern design.

Easy maintenance for cleaning and repair.

Automation and Security Systems

Smoke Damper System

Integrated system for fire safety:

Motorized dampers with automatic control.

Fire detection integration for rapid response.

Manual override for emergency control.

Position feedback for status information.

Maintenance alarms for preventive maintenance.

Automation System Installation

A fully integrated facility automation system:

SCADA system for central control.

PLC control units for local control.

HMI panels for operator interface.

Data acquisition for performance monitoring.

Alarm management for fault notification.

Existing Plant Integration

Data protocol conversion for system compatibility.

Network infrastructure for communication systems.

Backup for data security.

Operator training for system usage.

Transition planning for uninterrupted operation.

Electrical Installation Systems

Lighting Systems

Lighting to industrial standards:

LED technology for energy efficiency.

Lux values in compliance with occupational safety standards.

Emergency lighting as a safety system.

Automatic control with sensors.

Easy maintenance with long-lasting systems.

Power Distribution Systems

2500 kWa Transformer System

Oil-immersed transformer for high power.

Primary/secondary protection with relay systems.

Cooling system with fan control.

Oil analysis for condition monitoring.

Noise control for environmental protection.

MV-LV Switchgear

Medium voltage switchgear for 34.5 kV.

Low voltage panels for 400V distribution.

Protection relays as safety systems.

Measuring instruments for monitoring.

Arc flash protection for personnel safety.

Low Current Systems

Data network for computer systems.

Telephone exchange for communication.

CCTV system for security cameras.

Alarm systems for theft protection.

PA system for announcements and music.

High Current Installations

Motor feeders for production equipment.

Power outlets for general use.

Industrial sockets for heavy equipment.

UPS systems for uninterrupted power.

Generator connection for backup power.

Fire Detection Systems

Addressable system for point-based control.

Smoke detectors for early warning.

Heat detectors for temperature control.

Manual call points for emergencies.

Sirens and strobes as warning systems.

Earthing Installation

Foundation earthing as the main system.

Equipotential bonding for safety.

Lightning protection system.

Test points for easy measurement.

Copper conductor for low resistance.

Mechanical Installation Systems

Firefighting Installation

Comprehensive fire suppression system:

Sprinkler system for automatic suppression.

Hydrant system for manual intervention.

Foam system for special risks.

Fire pumps with redundancy.

Water tanks for sufficient reserve.

Ventilation Installation

Industrial ventilation solutions:

General ventilation for fresh air supply.

Local exhaust for pollution sources.

Pressure control for clean room standards.

Filtration for air quality.

Energy recovery with heat exchangers.

Heating and Cooling Installations

Climatic comfort systems:

Boiler system for heating.

Chiller system for cooling.

AHU units for air handling.

Fan coil units for local control.

BMS integration for central control.

Process Lines

Specialized installations for production processes:

Compressed air for pneumatic systems.

Vacuum lines for special applications.

Process water for production.

Flue gases for exhaust systems.

Chemical lines for safe transport.

Water Systems

Clean and wastewater management:

Potable water for hygienic distribution.

Industrial water for production.

Wastewater collection before treatment.

Rainwater for the drainage system.

Recycling for water conservation.

Finishing Works

Hygiene Areas

WC Blocks

Ceramic tiling for hygienic surfaces.

Stainless steel fittings for durability.

Ventilation for odor control.

Lighting for adequate light levels.

Water-saving fixtures for economy.

Locker Rooms

Personal locker system for secure storage.

Benches for comfort.

Ventilation for moisture control.

Anti-slip flooring for safety.

Shower cabins for hygiene.

Test Rooms

Teardown Test Room

Special-purpose testing area:

Reinforced flooring for heavy loads.

Special ventilation for dust control.

Sound insulation for noise control.

Lighting for detailed work.

Safety equipment for personal protection.

Tensile Test Room

Material testing laboratory:

Test equipment foundation with vibration isolation.

Power supply with high capacity.

Data acquisition for measurement systems.

Safety systems for personnel protection.

Calibration for precise measurement.

Water Storage System

750 m³ Underground Greywater Tank

Large-capacity tank for wastewater management:

Structural Features

Reinforced concrete structure with waterproofing.

Waterproofing with a membrane system.

Ventilation for gas release.

Access ladder for maintenance.

Level measurement for automatic control.

System Components

Inlet channels for wastewater collection.

Filter system for solid particle separation.

Pump system for discharge.

Alarm system for overflow protection.

Cleaning system for easy maintenance.

Landscape and Infrastructure

On-site Transportation

Asphalt roads for vehicle traffic.

Pedestrian walkways for safe access.

Parking areas for personnel and visitors.

Loading ramps for logistics operations.

Traffic signs for safety control.

Landscape Arrangement

Green areas for environmental balance.

Irrigation system with automatic control.

Outdoor lighting for security lighting.

Seating areas for personnel comfort.

Perimeter walls for security boundaries.

Infrastructure Systems

Electrical infrastructure with cable trenches.

Communication with a fiber optic network.

Natural gas for energy supply.

Fire department access with emergency routes.

Security systems for perimeter protection.

Industrial Door Systems

Logistics Doors

For loading and unloading operations:

Sectional doors for quick opening.

Dock levellers for height adjustment.

Dock shelters for airtightness.

Traffic lights for safety control.

Vehicle sensors for automatic control.

Emergency Exit Doors

Safety doors compliant with fire regulations:

Panic bar system for emergency opening.

Fire resistance of class EI 60.

Automatic closing for security.

Emergency lighting for visibility.

Alarm system for unauthorized use.

Security Features

Card reader for access control.

Intercom system for communication.

CCTV integration for video recording.

Anti-vandal design for durability.

Manual override for emergencies.

Project Management and Quality Control

Construction Phases

Ground preparation and improvement works.

Infrastructure works for foundations and utilities.

Steel erection for the structural system.

Cladding works for roof and facade.

Utility installation for MEP systems.

Finishing works and final layers.

Testing and commissioning.

Quality Assurance System

ISO 9001 for quality management systems.

Material testing with laboratory analyses.

Manufacturing inspection with process audits.

Final inspection with acceptance tests.

Documentation with as-built drawings.

Occupational Safety

HSE plan with risk analysis.

Personal protective equipment (PPE).

Safety training for awareness.

Emergency plan with response procedures.

Accident reporting for continuous improvement.

This comprehensive industrial facility project is equipped with the infrastructure to support modern production technologies and is built with high-quality standards and safety measures. The project, with its advanced automation systems and integrated solutions, will provide long-term operational efficiency.