This project, implemented by Borusan EnBW in Balabanlı, involves the installation of six wind turbines and the construction of the related infrastructure, with the aim of making a significant contribution to sustainable energy production. The project has completed all critical components, including turbine foundations, auxiliary structures, access roads, and drainage systems, in accordance with the highest engineering and safety standards.
Turbine Foundations and Platform Manufacturing
The most critical phase of the project was the foundation construction, which was carried out to ensure that each turbine could withstand high static and dynamic loads. This process began with the excavation of the foundation areas, followed by the pouring of grout to create a solid foundation. Formwork and rebar installation were carried out to create the main load-bearing structure of the foundations, after which the reinforced concrete construction of the turbine foundations was completed.
Anchoring systems that provide a secure connection between the turbine tower and the foundation, as well as electrical conduit piping for energy transmission, were integrated prior to the reinforced concrete pouring. Finally, grout was poured to strengthen the structural integrity of the foundation and fill any voids.
To protect the foundations from groundwater and moisture, waterproofing and drainage system applications, another important component of the project, were implemented. This waterproofing system ensures the long-term durability of the structures.
Logistics and Auxiliary Structures
The installation of turbines is a complex logistics operation that requires the transportation and assembly of heavy and bulky equipment. For this reason, transportation routes and turbine installation platforms have been constructed with great care for the turbine installation project. Excavation and filling works carried out in accordance with the challenging conditions of the terrain have ensured the safe movement of heavy cranes and transport vehicles. These roads and platforms have been delivered in compliance with test standards and made ready for operational use.
In addition, two warehouse buildings were constructed to meet the logistics and storage needs of the project site. These warehouses are critical for the safe storage of equipment and the effective management of site operations.
Infrastructure and Environmental Arrangements
To ensure the durability and sustainability of transportation routes, water ditches were constructed according to the topography of the land. At road crossings, reinforced concrete culverts compliant with DSİ (State Water Works) standards were built to control surface water flow. These infrastructure works guarantee safe transportation and drainage management throughout the project's operational lifespan.
The Borusan EnBW Balabanlı RES Project is a prime example of how turnkey projects in the wind energy sector can be successfully executed. Every stage, from the initial site surveys to the completion of the turbine foundations, logistics, and infrastructure work, was carried out without compromising quality and safety standards.