There are 13 projects.
sort Sort by:

Construction of 1 Turbine, Switchyard, Control Building, Access Roads, and Culverts
32,000 m³ excavation and 26,000 tons of fill,
Total Installed Capacity: 6.2MW

Installation of 21 Turbines, Construction of Switchyard and Control Building, Construction of Access Roads
15,285 meters of Ø40 and 880 meters of Ø100 bored piles,
525,000 m³ of excavation and 400,000 tons of backfill,
10,000 m³ of concrete and 2,000 tons of construction steel
Total Installed Capacity: 100MW

Electrical, Mechanical, and Infrastructure Relocation for the Installation of 1 Turbine, and Turbine Foundation Construction and Infrastructure Works
Total Installed Power: 4.8MW
Construction of 2 Turbine Platforms, Foundations, Access Roads, and Culverts
Total Installed Capacity: 6.8MW

Installation of 25 Turbines, Construction of Switchyard and Control Building, Construction of Access Roads
Total Installed Capacity: 104MW

Construction of 12 Turbine Platforms and Foundations, Switchyard and Control Building, Transportation Roads and Culverts
Total Installed Capacity: 30MW

3 Turbine Platform and Foundation, Transportation Routes and Culverts Construction Work
Total Installed Capacity: 18.9MW

1 Turbine Platform and Foundation, Transportation Routes and Culverts Construction Work
Total Installed Capacity: 6.8MW

Construction of 6 Turbine Platforms and Foundations, 2 Storage Buildings, Access Roads, and Culverts
Total Installed Capacity: 36MW

Construction of 21 Turbine Platforms and Foundations, Switchyard and Control Building, Transportation Roads
Total Installed Capacity: 55MW
8 Turbine Platform and Foundation, Transportation Routes and Culverts Construction Work
Total Installed Capacity: 56MW

Installation of 30 Turbines, Construction of Switchyard and Control Building, Construction of Access Roads
Total Installed Capacity: 77.4MW

Installation of 17 Turbines, Construction of Switchyard and Control Building, Construction of Access Roads
Toplam Kurulu Güç:24MW