This project, carried out by Bursa Temiz Enerji A.Ş. in Bandırma, includes the installation of a total of 17 wind turbines, the construction of related switchgear facilities, and the construction of a control management building. This complex project, aimed at making a significant contribution to sustainable energy production, has completed all processes from site preparation to the final installation of the turbines in accordance with the highest engineering and safety standards.

Site Preparation and Turbine Foundation Construction

The first and most critical phase of the project began with detailed site surveys and work planning tailored to the topographical and geological structure of the site for each turbine. These preliminary studies ensured that all construction processes were carried out flawlessly and efficiently.

To ensure that each turbine can withstand high static and dynamic loads, reinforced concrete foundation construction was carried out with meticulous care. This process continued with the pouring of grout to create a solid foundation after the excavation of the foundation areas. Formwork and rebar installation were performed to create the main load-bearing structure of the foundations, followed by the completion of the turbine foundation reinforced concrete construction. Anchoring systems that provide a secure connection between the turbine tower and the foundation, as well as electrical conduit for power transmission, were also installed prior to the reinforced concrete pour. Finally, grout was poured to reinforce the structural integrity of the foundation.

In order to protect the foundations from groundwater and moisture, waterproofing and drainage system applications, which are another important component of the project, have been implemented. This waterproofing and drainage system ensures the longevity of the structures.

Logistics and Infrastructure Manufacturing

The installation of 17 turbines is a complex logistics operation that requires the transportation and assembly of heavy and bulky equipment. Therefore, transportation routes and turbine installation platforms were constructed with great care for the turbine installation in the project. Excavation and filling works carried out in accordance with the challenging conditions of the terrain ensured the safe movement of heavy cranes and transport vehicles. These roads and platforms were delivered in compliance with test standards and made ready for operational use.

To ensure the durability and sustainability of the transportation routes, water ditches were constructed according to the topography of the terrain. At road crossings, reinforced concrete water culverts compliant with DSİ (State Water Works) standards were built to facilitate the controlled drainage of surface water flow.

Switchyard and Control Building Construction Works

The switchyard and control management building, which are the heart of the wind power plant, have also been completed as part of this comprehensive project. The switchyard ensures the safe transfer of generated energy to the grid, while the control management building enables the 24/7 monitoring, control, and management of all operational processes of the facility.

This project is an example of how turnkey projects in the wind energy sector can be successfully executed. Every stage, from the initial site surveys to the completion of the turbine foundations, logistics, and infrastructure work, was carried out without compromising quality and safety standards.